The Lighthouse is a 43-unit multi-family condominium with underground parking and amenity rooms on the shore of Georgian Bay, Ontario. The triangular, steeply graded site was difficult to build on: bordered by rock cuts, with limited setbacks and a history of industrial use.
Greystone (serving as developer, general contractor, and ICF installer) knew how to design the building around those conditions. It rises three storeys at the rear and five storeys on the waterfront side. A parking garage sits between levels to help manage the grade while keeping the building within local height restrictions.
Amvic™ ICF was used for 99% of the building, including exterior walls, interior walls, retaining walls and the parking garage. In total, approximately 75,485 square feet of ICF was installed. The company has been building with ICF since 1998 and has used it on most of its projects over the past decade.
The $15.4M development was finished early 2023 after 105 weeks of construction.

Using One Wall System Across the Building
Large commercial and multi-family developments can become more difficult as the number of wall assemblies, trades and construction sequences increases. At The Lighthouse, Greystone used reinforced ICF walls for several jobs that might otherwise have required different construction methods.
Amvic™ ICF formed the exterior envelope and interior walls while also serving as shear walls, retaining walls, parking-garage walls and fire separations.
Using one construction method across these applications allowed the crew to continue installing ICF rather than switching between framing and masonry systems. Greystone reported that this reduced construction complexity and the number of trades required on site.
The triangular property required a building footprint with numerous corners. Steep grades created stepped walls and changing bearing elevations, while the waterfront elevation had to accommodate large balconies and extensive window openings.


Reinforced concrete lintels were incorporated into the ICF walls above the large openings. Reinforcing for balconies and other structural connections could also be incorporated directly into the concrete wall system.
Building Through a Northern Ontario Winter
Construction schedules in northern climates can lose substantial time when wall systems depend on weather-sensitive installation.
The Lighthouse was built through the freezing temperatures and strong winds of a Georgian Bay winter. Greystone reported that ICF installation continued without the additional heating and hoarding that would otherwise have been required for portions of the construction.

The company estimates this ability to work through winter saved approximately two months on the construction schedule. And despite COVID-19 restrictions, ICF installation itself only took 165 days.
Greystone attributed The Lighthouse as fast to occupancy in part because of its ICF construction.
Scaling ICF Without Adding Construction Cost
Greystone reported no additional construction cost from choosing ICF for The Lighthouse. Its crews install the system themselves, and the company stated that its ICF construction costs can match or fall below conventional framing and other construction methods.
After decades of ICF work, Greystone has developed repeatable installation techniques and details that can be carried from one building to another. The company uses traditional construction methods alongside ICF to create customized façades without treating every architectural feature as a completely different structural system.

The Lighthouse pairs the concrete structure with precast hollowcore floors. According to Greystone, the modular qualities of the two systems worked well together while helping the design minimize the plenum space required for mechanical systems.
For developers considering ICF across multiple buildings or future phases, this repeatability is significant. Crew familiarity can remove part of the learning curve from subsequent projects while allowing many of the same wall details and construction sequences to be reused.
Turning a Difficult Site Into Developable Land
Before building construction could begin, the property required eight months of rock blasting, grading and soil remediation.
The land had previously been used as a rail spur and included contaminated soil from its industrial history. The irregular bedrock surface left after blasting required stepped walls, multiple jogs and variable foundation bearing elevations.

The grade differential also produced substantial retaining requirements: some basement walls retain as much as 12 feet of grade per level. Greystone used 10-inch ICF walls with increased reinforcing in these areas.
The parking garage sits between floors, helping bridge the elevation change from the rear of the property to the waterfront. The resulting building rises three storeys at the back and five on the Georgian Bay side while remaining below structures behind it.
Lower Heating Costs After Occupancy
Construction cost and schedule are only part of the financial equation for a multi-family owner.
The Lighthouse uses ICF exterior walls together with R-60 roof insulation, spray foam at transitions between dissimilar materials and low-energy HVAC equipment. Timber overhangs limit incoming summer sun while allowing more solar gain during winter.
Greystone reports average annualized heating costs of approximately $15 per month per condominium unit. The company estimates this at roughly 85% below the heating cost of a single-family home in central Ontario.
Greystone paired the insulated building envelope with LED lighting, low-water-consumption fixtures and individually controlled HVAC systems. Owners can remotely manage temperature, security and access through the building’s SmartONE system.
Concrete Walls Between Units
The concrete construction also addressed two concerns common to multi-family buildings: fire separation and sound transfer.
Greystone used ICF walls as fire separations within the development rather than introducing a separate wall type for those locations. The concrete construction also reduces sound transfer between units, an important consideration in a condominium development where privacy directly affects the resident experience.
From Difficult Property to Future Development
The Lighthouse reached completion on schedule despite winter construction, COVID-19 restrictions, material-market volatility and a site that required extensive remediation before the building could begin.
Greystone reported strong sales and resale values after completion. The developer has since purchased additional contaminated waterfront land for future phases based on the same general building concept.
The Lighthouse was also named the low-rise multi-family and People’s Choice winner at the 2024 ICF Builder Awards.

For developers, the project provides a clear example of Amvic™ ICF used at commercial scale. Greystone used one wall system across almost the entire building, saved an estimated two months by building through winter and reported no added construction cost. Owners also benefit from very low reported heating costs after occupancy.
Learn more about Amvic™ ICF here. Interested in constructing a large project with ICF? Speak to a rep local to you at https://alleguard.com/account-manager-search/