The Delta Terra Campus in San Antonio, Texas, was designed as a compact commercial gym on a constrained urban site near San Antonio International Airport. The completed building contains 2,170 square feet of floor area plus a 640-square-foot mezzanine, with 77% of the building constructed using ICF and all exterior walls formed with Amvic™ ICF.
Designed by Architectura SA and developed by Delta Terra Group, the building pairs curved ICF walls with a self-spanning Quonset-style metal roof. The form draws from aviation design, using sweeping roof lines, curved concrete walls, elevated end walls and corner glazing to reference the profile of aircraft wings, fuselage and cockpit windows.

The project was completed in December 2020 for approximately $525,000. Amvic™ ICF installation took 12 days within a 32-week construction schedule, helping save approximately four weeks compared with alternative construction methods. Using ICF also avoided an estimated $30,000 in added costs that would have been required to achieve the building’s curved wall geometry through another construction system.
Using ICF to Simplify a Complex Building Form
The building was designed around the structural properties of reinforced concrete rather than adapting ICF to a conventional framed building.
Curved Amvic™ ICF walls establish the profile for the Quonset roof, allowing the roof panels to anchor directly into the concrete walls through custom bent-steel anchor plates. Because the roof panels are structurally self-spanning, the assembly did not require a separate roof framing system.
At the rear of the building, additional reinforcement was introduced to resist roof reaction loads. A reinforced concrete beam bears on the ICF formwork and incorporates embedded plates and additional anchors at the lower wall.
The front façade introduced another structural challenge. Four corner windows required reinforced cantilevered concrete wall sections, while the central entrance uses a raised roof profile supported by two curved ICF end walls poured approximately 21 feet above the finished floor.

Four Weeks Saved Through Fast ICF Installation
The ICF portion of the project was installed in 12 days, contributing to approximately four weeks of schedule savings across the overall construction program.
The system also reduced the number of separate structural assemblies required in the building.
The exterior walls use Amvic™ ICF. The Quonset roof panels span without joists or trusses and anchor directly to the concrete walls. The mezzanine uses six-inch Hebel slab panels supported by the ICF walls. Together, the systems allowed the building to be completed without conventional joist or truss framing for either the roof or mezzanine.

For a commercial developer, the result is significant because fewer structural components can mean fewer interfaces between systems, less staging and a more direct construction sequence.
Building on a Constrained Commercial Site
The 0.39-acre site presented logistical restrictions before construction began. An existing building occupied nearly half the property and had to remain operational and accessible throughout the work.
Selecting ICF early allowed much of the construction activity and material staging to remain within the footprint of the new building.
Space was particularly limited along the rear property line, where the new wall was built approximately five feet from the boundary while still leaving enough room for required parking. The rear wall also had to meet fire-separation requirements. The project team used the ICF wall assembly as part of its strategy for obtaining code approvals and additional municipal exemptions, citing its four-hour fire rating together with the noncombustible metal roof system.
Construction then encountered another complication when work coincided with the beginning of the COVID-19 shutdowns in San Antonio. Commercial construction was permitted to continue, allowing the ICF installation and concrete pours to proceed while crews adapted to new distancing requirements and material shortages.
Precision in Curved Concrete Construction
The curved roof geometry required the ICF installation to match prefabricated metal roof panels that had already been manufactured before arriving on site.

ICF Constructors pre-assembled the blocks on the ground, measuring, cutting and marking individual pieces before installation. The radius of the walls had to correspond closely with the finished Quonset panels so the two systems would meet cleanly after assembly.
The raised walls at the central entrance added another layer of difficulty. The crew had to match the upper roof curve while simultaneously aligning the underside of the elevated walls with the lower roof profile.
To complete the detail, the installer created custom curved formwork and an extensive bracing system capable of supporting the walls approximately 21 feet above the floor during the concrete pour. Embeds and wall penetrations were installed as part of the same work.
Reducing Cooling Demand in Texas
Energy performance was another part of the building strategy.
In San Antonio, cooling represents one of the major operating loads for commercial buildings. Delta Terra combines its ICF envelope with a commercial variable refrigerant flow air-conditioning system and closed-cell roof insulation. The project team designed the systems together so the lower cooling demand created by the insulated, airtight envelope could be reflected in the HVAC strategy.
Architectura SA had previously worked with the local utility to establish a rebate recognizing ICF construction in San Antonio. The firm intended to use Delta Terra’s post-occupancy utility data to study how ICF and the VRF system performed together and to support wider adoption of similar rebate incentives in the region.
For developers evaluating ICF on larger commercial projects, this relationship between envelope performance and mechanical demand can be as important as the initial wall construction. Lower heating and cooling requirements have the potential to affect operating expenses throughout the life of the property, although the project documentation does not provide completed post-occupancy utility figures.
One System Serving Many Roles
Approximately 2,888 square feet of ICF was used across the project, including 2,795 square feet of exterior ICF wall area.
In this building, the Amvic™ ICF walls perform several jobs at once. They form the reinforced exterior structure, provide continuous insulation, create the building’s curved architectural profile, carry roof reaction loads, support the mezzanine system and provide anchorage for the self-spanning metal roof.

The system also helped address the narrow site’s fire-separation requirements while allowing the design team to avoid adding a separate structural roof frame.
That consolidation is particularly relevant as projects grow in size. Repeating a wall assembly capable of performing structural, thermal, fire-separation and architectural functions can reduce the number of separate construction systems a developer has to coordinate.
A Commercial Building Designed Around ICF
The completed building retains the structural materials as part of the architecture rather than concealing them behind a conventional building form.
The curved metal roof follows the geometry established by the ICF walls. A raised central entrance creates a second roof profile, while four frameless corner windows reference an aircraft cockpit. The 640-square-foot mezzanine adds usable floor area within the building’s compact footprint.

The owner, whose business is connected to aviation, selected the building’s location less than a mile from San Antonio International Airport. According to the project team, the aviation-inspired architecture and industrial material palette were major parts of the owner’s satisfaction with the completed building.
The Delta Terra Campus was named the Light Commercial Winner and People’s Choice Winner at the 2022 ICF Builder Awards.