The Alexander Muskoka Residence brings 102 retirement suites to the shores of Lake Muskoka in Gravenhurst, Ontario, including 30 units considered affordable under CMHC standards.
Designed by Craig England of PH43 Architecture and built by Greystone, the 77,223-square-foot development had to fit onto a constrained waterfront property while preserving water views from existing homes. Those restrictions influenced the building’s height, footprint and exterior design.
Greystone selected Amvic™ ICF R30 for 100% of the exterior walls. A total of 36,244 square feet of ICF wall was installed, along with 26,880 square feet of two-inch Envirosheet® insulation beneath the slab.
The choice formed part of a larger value-engineering effort that reduced the projected development cost from $28 million to approximately $20 million without compromising the original scope. The use of ICF also helped Greystone shorten the construction schedule by an estimated six months.

Bringing a $28 Million Plan Down to $20 Million
Affordability placed additional pressure on the construction budget. With 30 of the residence’s 102 units designated as affordable, Greystone had to find savings without reducing the size, performance or intended use of the building.
One of the changes was moving away from the originally proposed double wood-framed exterior walls in favour of Amvic™ ICF.
ICF allowed the structure and insulation to be installed as one wall system. The reinforced concrete walls also served as shear walls, eliminating the need to introduce separate structural wall systems in areas subject to lateral forces.
For a development of this size, maintaining the same construction method across the exterior meant crews could continue installing ICF rather than switching between different structural assemblies.
The change formed part of the value-engineering work that reduced the projected development cost by approximately $8 million. The final construction cost was $19.5 million.
Building 36,244 Square Feet of ICF Through a Muskoka Winter
Construction on the shores of Lake Muskoka meant dealing with subzero temperatures and strong winter winds.
Under the direction of project manager Chris Touesnard and site supervisor Andrew Webber, Greystone installed 36,244 square feet of Amvic™ ICF exterior walls over 221 days.

The insulating properties of the forms helped protect the concrete during cold-weather construction. Greystone reported being able to continue ICF construction through the winter without additional heating and hoarding.
The residence was completed in 106 weeks, with Greystone estimating a six-month construction time saving from using ICF.
Fitting a Large Building Onto a Difficult Site
Months of rock blasting and grading were required before construction could begin. Even after blasting, the remaining rock surface was irregular. Greystone addressed these conditions with stepped foundation walls, variable bearing elevations and multiple jogs.

Space around the building was also limited. The southwest elevation borders a cliff edge, leaving little to no exterior access from one side and complicating the installation of exterior finishes.
Plumwall bracing systems helped crews maintain straight and square walls across the building’s long elevations.
The waterfront location presented another structural requirement. Large windows and extensive openings were needed to take advantage of views across Lake Muskoka. Reinforced concrete lintels formed within the ICF walls provided a cost-effective solution without introducing a separate structural system around the openings.
Maintaining Construction Efficiency at Scale
Using Amvic™ ICF throughout the exterior allowed Greystone to address several structural requirements within a single building system.
In addition to forming the insulated exterior walls, the reinforced concrete served as shear walls to resist lateral forces. Crews could maintain the same installation process across different sections of the building without switching materials.

Structural connection details were also incorporated directly into the ICF walls. In selected areas, portions of the foam were removed before concrete placement to bring the concrete flush with the exterior face of the insulation. This allowed structural ledger boards to be installed directly against the concrete at the required plane.
These details allowed Greystone to accommodate different structural requirements while maintaining a consistent construction method across more than 36,000 square feet of exterior wall.
Lower Energy Demand Across 102 Units
Energy performance was a major consideration for a retirement residence occupied year-round.
Amvic™ ICF R30 walls were paired with triple-glazed windows to create a highly insulated, airtight building envelope. Two inches of Envirosheet® rigid EPS insulation were installed beneath 26,880 square feet of slab area.

Craig England also incorporated building orientation and natural ventilation into the design to take advantage of solar gains where possible. LED lighting, ENERGY STAR appliances and high-efficiency heat recovery ventilators further support the building’s energy performance.
Average heating demand has been reported at 2.56 kWh/m² per month over the six-month heating period. Average cooling demand is 0.80 kWh/m² per month over six months.
The reported heating demand approaches Passive House performance levels. Across 102 suites and more than 77,000 square feet of floor area, low heating and cooling demand can translate into significant long-term operating savings.
The insulated concrete exterior walls also contribute to quieter indoor spaces and more stable interior temperatures, both desirable features in a retirement residence.
Designing Around Lake Muskoka
PH43 Architecture had to accommodate 102 retirement suites, parking and shared amenity spaces within a restricted building footprint. Zoning regulations also limited the building’s height to protect water views from existing homes behind the property.
Varying parapet heights and a mixture of Shouldice Designer Stone, StoCast wood finishes and ADEX architectural coatings break up the long exterior elevations. Natural earth tones complement the surrounding rock, trees and waterfront.

Inside, a large skylight brings daylight into the central atrium, providing residents with a comfortable gathering space. The building layout balances privacy, shared amenities and views across Lake Muskoka.
The reinforced concrete construction allowed England to incorporate extensive glazing while retaining the thermal and structural performance required by the development.

Delivering Affordable and Energy-Efficient Housing
The Alexander Muskoka Residence addresses a growing demand for affordable and accessible senior housing in the region.
Thirty of its 102 suites meet CMHC affordability standards. The building also meets the accessibility requirements of the Canada Mortgage and Housing Corporation’s National Housing Co-Investment Fund.
For Greystone, the decision also affected the economics and schedule of the development. Changing from double wood-framed walls to ICF formed part of a value-engineering program that reduced the projected development cost from approximately $28 million to about $20 million. Construction continued through a Muskoka winter, and the team estimates the approach removed six months from the schedule.


The result is a 77,223-square-foot retirement residence with 30 affordable units, low reported heating and cooling demand and a building envelope designed for long-term commercial operation.
The Alexander Muskoka Residence reached substantial completion in March 2024 and was named second runner-up in the multi-family category at the 2025 ICF Builder Awards. With closely spaced webs, multiple concrete core sizes, R22 and R30 options, continuous EPS insulation and a proven record on large buildings, Amvic™ ICF is the best ICF block for commercial construction.