The Maine Molecular Quality Controls expansion in Saco, Maine, gave Consigli Construction the kind of conditions heavy commercial builders routinely have to manage at once: a demanding schedule, tall concrete walls, steel and curtainwall interfaces, extensive MEP coordination, winter weather and an occupied facility that could not shut down.
The $17.151 million addition and renovation added 34,200 square feet for clean rooms, laboratories, quality control, research and development, manufacturing support and future fit-outs while renovating another 15,495 square feet of the existing facility. Approximately 21,000 square feet of Amvic™ ICF was used for the foundation, first and second levels and roof parapets.
The team included owner/developer Joan Gordon of Maine Molecular Quality Controls, Inc., architect Andy Tyner of SMRT, Consigli Construction general contractor Dave Thomas and Consigli ICF installer Larry Chouinard.

Building Tall Walls
The exterior walls presented challenges that went well beyond a standard commercial wall pour.
Floor-to-floor placements reached 15 feet and had to accommodate steel beam pockets and two-storey curtainwall openings. One wall extended 36 feet from grade to the penthouse without an intermediate slab to interrupt the construction. Chouinard and Consigli’s self-perform crews worked with a bracing system developed to stiffen the walls before concrete placement, while the team performed frequent checks on reinforcing steel, openings and wall alignment.
Full-height curtainwall openings added another level of coordination. Prebuck frames were installed at the two-storey openings, while Chouinard’s crews monitored plumbness throughout construction.
The result was unusually little correction once the walls were complete. At the 36-foot-high curtainwall opening, only minor planing and shimming of a small number of bucks was required before façade installation could proceed.
For large commercial builders, accuracy at this stage has a direct effect on the trades that follow. Misaligned openings, misplaced embeds or incorrect pockets can interrupt steel, glazing and façade work. Consigli’s approach was built around preventing those problems before they reached the next trade.

Advancing the Construction Schedule
Thomas and the Consigli team also changed how the floor slabs and walls were sequenced.
Rather than breaking the floor-to-floor wall placement into several smaller pours, Consigli used the Amvic™ ICF wall as part of the slab edge condition. The slab stopped below the second-floor decking on the interior while extending higher on the exterior, allowing the ICF to act as the pour stop and maintain a continuous form.
This reduced the number of placements required and allowed steel installation to begin before all concrete work was complete. Steel crews started while concrete work continued at the penthouse rather than waiting for the ICF to finish.

That sequencing is significant on a large commercial job. Saving time is not limited to installing one wall faster. The larger opportunity comes from allowing the next operation to start sooner and maintaining a consistent flow of work between concrete, steel and other trades.
Consigli coordinated the sequence closely between Chouinard’s self-perform ICF crews and the steel subcontractor so concrete progress continued to open work areas for steel.
Saving Time With an ICF Parapet
The original design called for a framed parapet. The team instead changed the assembly to ICF. Doing so required a large roof-level header, including a grade-beam tied into the block and spanning the window header.
The change saved 10 days on the construction schedule.
For Thomas and other contractors managing large buildings, this type of decision can carry more value than a simple material comparison. A wall assembly can influence framing, concrete work, follow-on trades and the overall path to enclosure.
Coordinating ICF With Steel, MEP & Curtainwall
Large commercial wall systems rarely exist independently of the rest of the structure.
At MMQCI, Chouinard’s ICF crews had to account for steel embeds, beam pockets, door openings, full-height glazing and numerous mechanical, electrical and plumbing penetrations. MEP sleeves and penetrations required more coordination than comparable work in conventional concrete formwork, making planning before installation especially important.
Consigli’s Virtual Design and Construction team developed installation plans and a tracking dashboard that broke the ICF work down block by block. Five different ICF block types were used in the foundation wall, giving foremen a clear reference for block locations and cuts before installation.
The same plans located penetrations for roof drains, electrical conduit and other building services. This reduced uncertainty in the field and helped limit incorrect cuts and wasted material.
The approach treated ICF installation as part of the project’s larger coordination process rather than as an isolated wall trade.
Getting the Reinforcing Steel Right
Concrete construction leaves little room for correction once a placement is complete, and ICF required particular attention to reinforcing steel.
Consigli’s project engineer conducted quality-control walkthroughs at least twice each week, while the full-time superintendent monitored reinforcing work through daily site checks. Reviews covered rebar, steel embeds, openings, MEP penetrations and other heavily detailed areas.
Chouinard’s crews also adjusted their installation method for the tall floor-to-floor walls. Instead of forcing ICF blocks down over more than 30 feet of standing reinforcing steel, the rebar was divided into sections. Six-foot lengths could then be fed down into the wall after blocks were installed.
The level of planning paid off downstream. Very little rework was required for embeds and pockets, allowing structural steel work to proceed with limited interruption.
For a heavy commercial contractor, that is where construction quality and schedule performance meet. Avoiding a mistake inside the wall also avoids disrupting the trade waiting behind it.
Building Beside an Operating Laboratory
Construction took place beside an active MMQCI facility that remained operational throughout the expansion.
The new building shared a wall with the existing space and included two pass-through connections between the old and new facilities. Thomas and the Consigli team had to plan MEP shutdowns around active manufacturing and laboratory operations so Gordon and MMQCI could continue working during construction.

The restrictions became more demanding after construction began at the onset of the COVID-19 pandemic. Crews worked in smaller groups, with additional separation between trades. This placed even more pressure on sequencing because fewer workers could occupy the same area at once.
Lean planning helped maintain workflow. Materials were stored on pallets for easier movement and inventory control, while laydown areas, equipment routes and no-storage zones were established before deliveries arrived.
Those practices helped Consigli keep construction moving without overwhelming the occupied site.
Keeping Work Moving Through Winter
Weather presented another challenge.
High winds during the Maine winter required Chouinard and the site team to rethink how lightweight ICF material was stored. Because the floors had been kept clear through Lean site planning, ICF materials could be moved inside, consolidated and tied back to columns. Additional material was stored in the site trailer when necessary.

For a large contractor, jobsite efficiency is closely tied to material handling. Clear floors, planned delivery locations and accessible inventory reduce unnecessary movement while also making it easier to respond when site conditions change.
Reducing Operating Demand After Construction
The decision by Gordon and Tyner to use ICF was also tied to building performance. The owner and architect made the decision to build with ICF despite not having previous experience with the system.
The facility contains laboratories and manufacturing spaces with demanding HVAC requirements. Different rooms must maintain controlled pressure relationships to manage airflow, and the building requires a large supply of outside air for laboratory operation.

Amvic™ ICF was selected in part for its insulation properties. The insulated concrete wall assembly helps reduce heat transfer through the exterior enclosure, supporting the building’s heating and cooling strategy.
For Gordon and MMQCI, the construction decision therefore extended beyond the build itself. Exterior wall performance can influence energy demand and operating costs for years after occupancy, particularly in buildings with high HVAC loads.
Finishing Ahead of the Contract Milestone
The project reached Certificate of Occupancy 24 days ahead of the contractual milestone and was delivered under budget, with 2.5% added change orders.
Thomas, Chouinard and the broader Consigli team used self-perform crews, VDC planning, Lean scheduling, detailed quality control and close coordination between concrete, steel, curtainwall and MEP trades.

Amvic™ ICF fit into that strategy by allowing the contractor to construct tall insulated concrete walls, sequence concrete and steel work together, replace the framed parapet, coordinate openings and penetrations before placement and move the structure forward without waiting for each scope to finish in isolation.
The Maine Molecular Expansion was named the Heavy Commercial and People’s Choice winner at the 2022 ICF Builder Awards.